Browse Forums Building A New House 1 Jul 13, 2010 11:42 am contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore 4Jul 13, 2010 5:03 pm Contracts signed Dec 09 OK to Start Sep 17 Slab Oct 6 Frame Oct 25,26 Windows and Gutters Oct 28 Bricks Nov 2 -20 Roof Finished Nov 10 Insulation and Gyprock Finished Nov 30 Locked Out Dec 13 Cupboards Installed Dec 17 Tile prep work Dec 26 Painter started Dec 30 Stormwater Jan 17 Tiles Jan 10-19 PCI Feb 2 Handover Feb 9 viewtopic.php?f=31&t=37120[size=85] Re: Carlswil's Statesman Tusmore 6Jul 13, 2010 6:24 pm contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore 7Jul 13, 2010 6:28 pm contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore 8Jul 13, 2010 6:31 pm contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore 10Jul 14, 2010 10:56 am contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore - Land settlement done 11Jul 15, 2010 11:06 am We sent our application off to Revenue SA to get an extension on the FHOG 26 week criteria. Hopefully it doesn't take them to long to assess it. Here are some of our colour selections. I'll put pictures up of some things, once I've charged my camera. I hope it all comes together ok, i'm a little concerned about how things are going to look. Exterior: tiles - Boral shadow grey bricks - Austral Settlers grey gutters, downpipes, window frames - paperbark Roller doors - wilderness front door - I think wilderness, but can't really remember Interior: Kitchen bench - Vulcan stone. We couldn't afford to upgrade, so went with the standard range. I really wanted gloss, but the colour selections lady talked us out of it. I've pretty well regretted that ever since, but worst case if we hate it, we'll change it once we're in Cupboards - Rock Salt. I'm not sure about these, and haven't seen any pictures on here of them. I can't remember what we chose for the laundry, bathroom and ensuite. I'll update this when I know. Paint colour - First Snow. We wanted a neutral colour. I wish we could change it now. We were looking at a display home on the weekend with grey walls (not light grey), and it looked really good. I wasn't overly pleased with the tile selections we were given. I think we more chose what we disliked the least, rather than what we liked. contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore - Land settlement done 12Jul 15, 2010 11:22 am Hi carlswil, great to see you have started your own thread. Congratulations on settlement. I love your house plan and am looking forward to seeing samples of the colours you have chosen. What a pain if you have to wait until October for a slab, that would drive me insane knowing that the land was ready to go. Fingers crossed it gets brought forward for you. Re: Carlswil's Statesman Tusmore - Land settlement done 13Jul 15, 2010 11:37 am Thanks Cous1981 I think the builder is waiting for the FHOG extension to be approved (not that this is relevant to them, but they think it is), and then we'll be released to construction. Hopefully this happens soon. I'm not a patient person and I'm sick of waiting. contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore - Land settlement done 14Jul 15, 2010 11:46 am I am exactly the same, I feel for you. Re: Carlswil's Statesman Tusmore - getting close 15Jul 19, 2010 3:12 pm Heard from the builder today, they will release us to construction on Friday. Finally seems like something might actually happen. Hopefully we don't have to wait too long until they go to site. contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore - getting close 17Jul 20, 2010 11:03 pm We got a letter from Revenue SA today. Our FHOG extension has been granted. That didn't take them very long to approve. When I spoke to them yesterday, they said it would be 2 - 3 weeks before we got a response. contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 Re: Carlswil's Statesman Tusmore - FHOG extension granted 19Jul 21, 2010 2:15 pm Congratulations! I hope things really start to speed up for you now! I will be watching Contracts signed Dec 09 OK to Start Sep 17 Slab Oct 6 Frame Oct 25,26 Windows and Gutters Oct 28 Bricks Nov 2 -20 Roof Finished Nov 10 Insulation and Gyprock Finished Nov 30 Locked Out Dec 13 Cupboards Installed Dec 17 Tile prep work Dec 26 Painter started Dec 30 Stormwater Jan 17 Tiles Jan 10-19 PCI Feb 2 Handover Feb 9 viewtopic.php?f=31&t=37120[size=85] Re: Carlswil's Statesman Tusmore - FHOG extension granted 20Jul 21, 2010 2:17 pm Thanks Cous and Lucene. I hope things speed up too. As soon as there is some movement at my block, I will take pics and put them up. Now that will be exciting (well for me anyway) contract signed: Nov 09 Released to Construction: 23 Jul 10 Slab poured: 9 Aug 10 Frame completed: 30 Aug 10 Windows & Gutters: 7 Sep 10 Bricks: 15 - 23 Sep 10 Roof: 24 Sep 10 Gyprock: 20 Oct 10 Lockup: 25 Oct 10 Kitchen: 27 Oct 10 Tiling: 6 - 9 Nov 10 Painting: 17 Nov 10 Carpet: 30 Nov 10 PCI: 15 Dec 10 Handover: 17 Dec 10 https://forum.homeone.com.au/viewtopic.php?f=31&t=35943 there should be ss cable so you can pull up bore pump for service 1 3166 can someone with more experience give me their insight? land is pretty much flat its pretty much at the top of a hill. left and right neighbours are flat in line with my… 0 7470 2 4387 |