Browse Forums Building A New House Re: Any surprises (cost) after contract signing? 4May 19, 2010 12:59 pm Built a Tribeca 44 with the Big M Sales Accept 15/06/09, Contract Signed 24/09/09, Site Start 23/11/09, Slab 11/12/09, Frame 12/01/10, Roof 20/01/10, Lock-up 30/03/10, Fixing 30/04/10, Handover 27/08/10. Re: Any surprises (cost) after contract signing? 8May 19, 2010 11:52 pm wow jxh that is a few dramas hope its all smooth sailing from now on for you.. Budde Design 3D Architecural Visualizations, Architectural Rendering, Artist Impressions, 2D & 3D floor plans http://www.buddedesign.com nathan@buddedesign.com Re: Any surprises (cost) after contract signing? 9May 20, 2010 10:00 am Thanks everyone for your reply. We just signed the contract and waiting for the bank to approve our loan and council to get building permit. In the mean time demolishing the existing building. Another soil test needs to be done on the land. That is a worry. We already have fixed priced contract. Re: Any surprises (cost) after contract signing? 10May 20, 2010 1:59 pm We've just signed off on our final contracts, plans and pre-start variations....and today the builder tells me that there is a change in the finished floor level as per shire requirements. So they'll have to check it out and have the plans changed accordingly, and issue another variation....which may involve additional costs!!! Dont know how much yet 12 March 2010 - Land titles received 3 April 2010 - Signed building contract 14 April 2010 - Prestart 28 April 2010 - Loan approved 30 June 2010 - Slab completed 27 August 2010 - Brickwork completed 22 September 2010 - Roofing completed 30 September 2010 - Internal walls plastered 12 October 2010 - Lock Up 19 November 2010 - PCI 26 November 2010 - Handover 29 December 2010 - Moved In https://forum.homeone.com.au/viewtopic.php?f=31&t=32584 Re: Any surprises (cost) after contract signing? 11May 26, 2010 10:18 pm Although we told the builder that we didn't see the need for temp fencing (to which he agreed. He actually said the fencing was more for keeping their rubbish in, as opposed to keeping everyone out!), we found out just today that they've just put it in (we've just had our land excavated). This is a surprise cost to me! Could anyone please give me an indication as to how much they paid for temp fencing, per metre? Thankfully, it's only the front of our land that needs the fencing and this is only 14-15mtrs. Re: Any surprises (cost) after contract signing? 12May 26, 2010 10:22 pm We only needed the front too (21m frontage) and from memory it cost $480. Built a Tribeca 44 with the Big M Sales Accept 15/06/09, Contract Signed 24/09/09, Site Start 23/11/09, Slab 11/12/09, Frame 12/01/10, Roof 20/01/10, Lock-up 30/03/10, Fixing 30/04/10, Handover 27/08/10. Re: Any surprises (cost) after contract signing? 13May 26, 2010 10:27 pm jimmalenko We only needed the front too (21m frontage) and from memory it cost $480. Thanks kindly, jimmalenko. I'm not overly happy about spending another few hundred on something that I don't think we really need... but, if this is the worst thing that happens to us, then I think we're flying! You talk about deletions, are they variations or PS and PC adjustments? pleas list them 1 16571 We were lucky in that our old house was so small (86 square metres) compared to the new house, they were able to take enough readings around the old backyard house before… 8 37162 multiple occ properties are always billed by trades at a premium, rarely per sqm for the lot. You either have trades you know whoe will do by sqm or youre going to get… 1 2257 |