Browse Forums Building A New House Re: Is my builder very slow? 3Feb 23, 2010 5:40 pm Building in Mooroolbark! Building permit: 21.10.09 Site Start: 12.11.09 Slab 23.11.09 Frame completed 18.12.09 Roof completed 15.01.10 Lock up 05.03.10 Fixing : 30.04.10 Handover: 11.06.10 Blog: http://kelnryan.blogspot.com Re: Is my builder very slow? 19Mar 13, 2010 1:55 am Bit late to the party here, but it can be frustrating waiting with nothing happening. I was in a similar situation, and to make it worse one of my other mates was also building. We started at basically the same time, yet after 2 months they were pretty much at lockup and i was only just getting a roof! My builder have certainly pulled there finger out in the last 2.5 months because i'm pretty much finished, and slightly (very slighty!) in front of them. So i guess the message is, whilst they may be dragging their feet now, you never know what's around the corner. Just try not to *** them off too much hownding them with questions Re: Is my builder very slow? 20Apr 08, 2010 8:15 am Thank you for your replies @Elemist...I can only pray that he does something.The frames went up around 2-3 weeks back. Now he is waiting for bricklayers...he can't find any and is not sure whether he will be able to find any in the near future Hi Lomarg, sounds like you're dealing with quite a commmon issue in construction projects, here's how I would look at handling it. Start by recognising the progress made… 1 3926 Hi Mofflepop, I would recommend finding a building designer to prepare plans, they should design to your specified budget. The benefit is you can tender the project out… 9 50104 Hello Team, I'm a new builder and I would like to apologise upfront if this question has already been asked and answered. We are 3 friends and each of us are looking to… 0 13915 |