Hi,
We officially completed the M 'fixing stage' today, which means that are now onto the 'completion stage'. For those who have built with M, how many days did they take to complete the house during the 'completion stage'?
Browse Forums Building A New House Re: Building with M - how many days in 'completion stage' 5Oct 16, 2009 2:39 pm Hi, we are also building with M and the fixing stage is almost finished as well. Our Site manager said that house will be completed by FEB NEXT YEAR!! ![]() So hopefully from what some of you are saying, we'll be in before xmas! Good luck to everyone ! ![]() 8 6685 I'll be here once a week, lets make that Mondays. 0 6765 ![]() Yep, should get an email similar to a variation email. Mine from MJH were a email with an attachment "Extension of time claim - inclement weather" - no mentions of price… 8 1949 |