Browse Forums Building A New House Re: Building with M - how many days in 'completion stage' 4Oct 02, 2009 10:09 pm i was just wondering the same thing! we also just started the completion stage with M. about 3 weeks ago our SS said we would not be done by christmas... they must really slow down if thats true. i just dont see how they can get to this stage so quickly and then cant manage to have the last stage finished in the next 2 months. Re: Building with M - how many days in 'completion stage' 5Oct 16, 2009 2:39 pm Hi, we are also building with M and the fixing stage is almost finished as well. Our Site manager said that house will be completed by FEB NEXT YEAR!! So hopefully from what some of you are saying, we'll be in before xmas! Good luck to everyone ! 8 6156 I'll be here once a week, lets make that Mondays. If you have a question, this will be the day I will log in for a look around.. If your lucky, sooner. Ask away...… 0 6369 Like I said the Occupancy Certificate is not the tollgate that marks the completion of the house. The contract defines… 7 10761 |