Firstly we were advised in an email from the builder that the house cost would be turn key at 170K with the slab being classed as a H slab. before we signed , we reviewed the contract ( a standard HIA contract) it was worded the inclusions were being based on an M Class slab. We questioned the builder about this and he then hand wrote in the additional terms section that the contract is a fixed price and will not differ regardless of soil type which he then signed and we signed as well . Are we covered here? We have now been told verbally that the land is worse then expected.. didnt know you could get worse then H
![Frown ::frown::](./images/smilies/Frown.png)
Dont get me wrong they have been fantastic with getting the price within our tight bidget with generous inclusions! And have had great customer service! Just very afraid of being burnt...
Oh wells
![Dizzy ::dizzy::](./images/smilies/Dizzy.png)