Yesterday I posted an update to my blog staying how well I thought the on site meeting went and how things seem to generally be running on time.
And I was trying to be all positive too.. but then I visited the site yesterday afternoon...
In Ventura's defence my brick supervisor did get right onto the problem that I bought up in the meeting. Particularily the fact that the shower plumbing was on the wrong wall and the gar points were in the wrong positions, he must have gotten onto the plumber straight after the meeting because by Monday afternoon the plumber had been back and fixed both those issues.
How ever this was the plumber that seemed unable to read a house plan in the first place and whilst it would appear he has down a good job, he has certianly created a further problem.
The plumber cut a horizontal chase into the wall to divert the gas pipe to where it was meant to be, which is good, however in doing so he cut clean through my Cat6 data cable, my coaxial cable and the power cable, which is NOT good. Now these weren't hidden, each of these cables were poking out of their sockets quite clearly, but it would seem that the plumber assumed that the cable came up out of the slab rather then down from the roof. So now I have to get my data cabler back in to re wire the lounge room for Networking ad Coaxial... oh well..