wait....15k? are you saying they're OVERDUE on the contractual completion date by 18 months? If so, i think LD might be the least of your worries. What stage is the house at?
Its 10 months... $50 x 30 x 10 = roughly $15000
Its 95% complete.. Builder has been promising to have PC soon since ages.. hopefully we can have by the end of this month.
It says calendar day so hoping I don't have to fight them with their possible argument saying business days.. lol
thats insane for a build to be sitting there that close to completion. Did you receive any extension notices on timing? That might undo your claim