Browse Forums Building A New House Re: Symmetric homes - job status, progress and quality 17Feb 08, 2022 7:34 am Since there are many PM enquiries about this builder and our job status. I'm posting here instead of replying everyone. Unfortunately our house handover is not done yet. I've a walk through tomorrow, will have an update by tomorrow. Awaiting to hear back from them on the details of fix made in the last 2 inspections. Fingers crossed for tomorrow. As per NOC our job started 22/03/2021, contract signed date Dec 2020. It's been 11 months since our construction started. Re: Symmetric homes - job status, progress and quality 18Feb 10, 2022 7:20 am jay4542 Since there are many PM enquiries about this builder and our job status. I'm posting here instead of replying everyone. Unfortunately our house handover is not done yet. I've a walk through tomorrow, will have an update by tomorrow. Awaiting to hear back from them on the details of fix made in the last 2 inspections. Fingers crossed for tomorrow. As per NOC our job started 22/03/2021, contract signed date Dec 2020. It's been 11 months since our construction started. Hi Jay, Good to hear you are getting your house handover soon. Please share your experience , the quality of finish work and your private inspector comments. Also is there any payments from builder for late completion . Thank you All the best! 1 4817 Thanks for much mate. I see that you do cabinets before flooring. For timber flooring, for most parts it's fine because it's got base plates, and for door jabs you can… 7 13035 8 6247 |