I'm building 2 townhouses side by side and going to subdivide. I need to install an underground pit for the electricity and filling out the application form for Jemena and have some questions
1. Do I need just 1 pit or do I need 2 pits (1 for each property)
2. What is the rate of supply (Amps and kW) that I should put on the application (already just my air conditioning for each unit is 23kW)
3. If I get a 3 phase pit installed by the Electricity company, is there anything on the builder side (electrician) that is needed extra. (ie, if the builder is assuming single phase in their quotation, if the supply is 3 phase is there anything that will be needed that would make the cost go up on the builder side)