Browse Forums Building A New House Re: Current Build Times 6Jun 29, 2021 7:59 pm I have more a more detailed breakdown of our timeline but at a high level; 29/07/20 - Plan Fee paid 01/10/20 - Signed Contract Tender ... Xmas break ... 05/02/21 - Construction started with a 130 business day construction period 30/06/21 - PCI walkthrough with SS So from breaking ground to handover we are looking at roughly 5 months, give or take. Follow my build here: https://www.instagram.com/ivy5custom Hi Minho I have heaps of experience in Ku-ring-gai with both DAs and CDC ( this is the main area we build in). DA's are taking 12-18months and CDC's we have been doing… 1 13732 We are having a bathroom reddone. The builders are putting down two coats of waterproofing and then screed and then another coat of waterproofing. This is what I have been… 0 13140 Thank you so much everyone. This all makes a lot of sense. I guess when you talk to a builder who butters up everything to look very polished, you get to start believing… 7 59157 |