Browse Forums Building A New House Re: Pre-Construction Timeline 2Apr 04, 2021 12:45 pm Follow my build here: https://www.instagram.com/ivy5custom Re: Pre-Construction Timeline 4Apr 04, 2021 1:37 pm So had a look at our timeline so far - my comment above stating less than a month was after everything had been finalised and we locked in a signed the final contract. The whole planning process did take some time though (about 8 months from first tender to breaking ground). 29/06/20 - First Tender 01/10/20 - Signed Contract Plan (after about 7 or 8 tender revisions) 27/10/20 - 5% deposit // internal and external colour selections done // 27/11/20 - CDC // 3 week closure over xmas // 01/02/21 - Signed Construction Plans 05/02/21 - Excavation started Follow my build here: https://www.instagram.com/ivy5custom The fastest thing a builder will do is bank your cheque, those systems work perfectly with lightning speed, everything else is slow burn. Just the way it is. 1 5613 We've had the offer of a short term tenant whilst waiting for CDC/DA home approval and demolition for our knock down rebuild. It would achieve a pretty low rent as it's… 0 9886 Just to makea point about this, an approach that some people have found sucessful in negotiating these rises down, Is to provide some workings to the builder, specifying… 4 64904 |