Week 15 Update - This week we see good progress. The lower roof tiles are now completed, Lower Fascia and Gutter have also been completed for Ground, Metal roof over the garage has been delivered and installed, AC duct pipes have also been installed in Ground and 1st floor. The scaffold has now been lowered and reset for lower roofs. For this week, the plan is to complete the Eaves and Ceiling for Ground floor, Electric Rough in and Water proofing for wet areas. I have booked Housepect for the pre-lining inspection on 21st Sep, so will await the reports. If all goes well, expecting to complete the lining of house by end of this month.