Hi All!
First time builder here! I have spent a lot of time reading through the other forums on here and have learnt so much already and so I thought it was about time I created my own thread
My partner and I are building a modified version of The Maldives with Homegroup WA and below is how far we are currently through the process:
Land and builder deposits paid - 27.05.2020
Final sketch and pre contract quote - 16.06.2020
Keystart finance application submitted - 24.06.2020
Finance pre-approval - 15.07.2020
Building contracts (only signed by us) - 23.07.2020
Contour survey completed - 31.07.2020
Progressed to siteworks department & received site plan - 11.08.2020
1st home buyers grant approval & rate of duty pre-approval - 21.08.2020
Finance formal loan approval - 26.08.2020
Settlement documents received countersigned and returned via post - 1.09.2020
Developer approval application sent - 2.09.2020
Developer application approved - 3.09.2020
First documents received - 6.09.2020
Tile and laminate meeting - 9.09.2020
Settlement invoice paid - 16.09.2020
Settlement finalised!! - 23.09.2020
Pre-start completed - 29.09.2020
Progressed to drafting department - 29.09.2020
Pre-start invoice paid - 01.10.2020
Progressed to scheduling department (approx. 4-6weeks till construction) - 02.10.2020
Building contracts signed by all parties - 02.10.2020
Build permit application sent to council - 13.10.2020
Building permit received - 19.10.2020
Earthworks started - 27.10.2020
Earthworks completed - 29.10.2020
Slab down - 03.11.2020
Brickwork begins - 23.11.2020
Would love to hear from others who are building!