Browse Forums Building A New House Re: Building with Wisdom Homes 15876Jul 06, 2020 9:04 pm malypetu Hi All, I've got a question regarding payments. In the contract state 20% Due on completion of brickwork or external cladding materials However, in the final document (yet to be signed), they've added: 20% Due of Completion of Brickwork. (no roof tiles laid) Is this something I need to worry? or should I ask to remove (no roof tiles laid) ? Cheers I think that's normal or at least what I've noticed on our contract, it also has the (no roof tiles laid). Hope that helps. Re: Building with Wisdom Homes 15877Jul 07, 2020 9:09 am M4bath malypetu Hi All, I've got a question regarding payments. In the contract state 20% Due on completion of brickwork or external cladding materials However, in the final document (yet to be signed), they've added: 20% Due of Completion of Brickwork. (no roof tiles laid) Is this something I need to worry? or should I ask to remove (no roof tiles laid) ? Cheers I think that's normal or at least what I've noticed on our contract, it also has the (no roof tiles laid). Hope that helps. Just to provide information for others. The contract (at least mine) did not have "no roof tiles laid". I've requested to be removed and it was, without issues. In terms of speed, CDC was meant to be ready before Christmas 2019, however, it was issued, after complaining many times, at the end of May. In actual fact, nothing has been done on our site and it is been a year since we start. Re: Building with Wisdom Homes 15879Jul 07, 2020 9:29 am malypetu M4bath malypetu Hi All, I've got a question regarding payments. In the contract state 20% Due on completion of brickwork or external cladding materials However, in the final document (yet to be signed), they've added: 20% Due of Completion of Brickwork. (no roof tiles laid) Is this something I need to worry? or should I ask to remove (no roof tiles laid) ? Cheers I think that's normal or at least what I've noticed on our contract, it also has the (no roof tiles laid). Hope that helps. Just to provide information for others. The contract (at least mine) did not have "no roof tiles laid". I've requested to be removed and it was, without issues. In terms of speed, CDC was meant to be ready before Christmas 2019, however, it was issued, after complaining many times, at the end of May. In actual fact, nothing has been done on our site and it is been a year since we start. It might have those words to indicate that although the frame, roof truss, bricks etc is done or time for payment is not an indication the roof tiles will be done by then. If you have removed it, does that mean it will be done as part of brickwork? Re: Building with Wisdom Homes 15880Jul 07, 2020 9:50 am manhattan52 the standard HIA contract says "lockup, the stage when a house's external wall cladding (brickwork) is installed, eaves lining and roof covering (tiles or steel) is fixed". Why does Wisdom Homes include a special clause i.e."no roof tiles laid" in their contracts to exclude the roof here? Can someone please offer some advice? Im DESPERATE. Because I'm completely and utterly exhausted. How long are variations taking with other companies at the moment? We… 0 11921 In fairness nobody gave a crap about the ACCC and the gag clauses continued in the pro forma templates of a few other builders after the ACCC took on Wisdom, and more… 20 57286 Hi Everyone, I am exploring builder in NSW and received a very tempting quote from Wisdom home for their momentum series. I just want to know experience of building… 0 3507 |