Thought i’d start my own thread on my build with Home Group WA since I’m still in the early stages.
Timeline so far:
23/04/19- Offer on block
06/05/19- Offer acceptance
16/05/19- Cat 2 check
31/05/19- Finance application
13/06/19- Bank valuation
21/06/19- Finance approval
18/07/19- Land settlement
19/07/19- HG confirm finance and land settlement
31/07/19- First documents received
12/08/19- Council planning application
26/08/19- Pre- start
19/09/19- Final documents received/ start of scheduling phase.
11/11/19- Council planning approval issued
13/11/19- External certification submitted
18/11/19- External certification received
19/11/19- Building permit application
20/11/19- Building permit issued.
27/11/19- Pre- site inspection
29/11/19- Removal of boundary fence.
04/12/19- Advised of movement to Construction phase.
09/12/19- Siteworks expected to commence
16/12/19- Siteworks commence (delay due to incorrect disposal during demolition and buried debris).
19/12/19- Footings Laid
21/12/19- Slab poured
20/01/20- Bricks Delivered
04/02/20- Brickwork commenced
17/02/20- Plate Height
18/02/20- Roof Carpentry commenced
11/03/20- Roof Cover complete
13/03/20- Ceilings and wall gyprock commenced
27/03/20- Painter sealed walls
01/04/20- Lock Up
06/04/20- Bath and plumbing fixtures
10/04/20- Cabinetry complete
20/04/20- Garage grano poured
22/04/20- Tiler commences
30/04/20- Tiling complete
04/05/20- Final electrical and plumbing
11/05/20- A/C, Solar, Insulation
12/06/20- PCI
25/06/20- Key Handover