Anyone want to share how long it took from your Canvas Quarter visit until there was action on your land?
I've got my CQ appointment next week, it's a greenfields build so no delays due to knockdown.
Hi big D,
We started canvas quarter in early August 2019 and just finished a week ago but still waitng on actual final paperwork to go to construction. All variations (which there was 26) were signed and returned within in 10 mins. The biggest hold up was deciding on a sky light when starting cq and then wanting to relocate the tank, this took 2 months which was estimating teams hold up not our CQ lady or our admin. Kitchen variations take forever to get back too as timpelle is slow...
Ours was also a new registered block so no knock down.
We hope to have slab mid next month.
So 7 months..... 😅 but we had a 3 week xmas break to contend with 🤷♀️
Good luck!