Browse Forums Building A New House Re: Building with Wisdom Homes 15336Nov 24, 2019 5:25 pm Femstar Stukip M4bath @Stukip - your signature shows slab down in March, 2019. Are you nearly at handover? Not yet. Ground floor tiling done last week. Final coat inside paint due next week with mirrors and shower screens. Expecting handover end January as have pool and other landscaping to do with Wisdom but date not yet confirmed. Hi Stukip, I’m pretty much in the same situation as you apart from the pool. WH is also doing my landscaping. End of January expected but not confirmed. Manhattan54, you should be getting close to PCI now? Femstar. Probably end of this week Re: Building with Wisdom Homes 15337Nov 24, 2019 8:24 pm Funk52 My build looks like it is close to complete, but my supervisor won't give me any estimates other than quoting when I am contracted to (which is well after when it should be finished). The final coat of paint and last bit of carpentry work will be completed this week. Only major work left after that is the main floor tiling and carpeting. The week after Wisdom will install the pool (8.5m x 3m fiberglass). Even if they can't finish by Christmas, it's not too much to expect them to finish soon after right? Hi Funk52, few of us are in similar situation. WH don’t want to commit to an estimated handover time. My SS only told me recently it might be end of January/ first week February. There is a 3 weeks close down which will slow every down in the new year I guess. Re: Building with Wisdom Homes 15339Nov 25, 2019 9:03 am Femstar Funk52 My build looks like it is close to complete, but my supervisor won't give me any estimates other than quoting when I am contracted to (which is well after when it should be finished). The final coat of paint and last bit of carpentry work will be completed this week. Only major work left after that is the main floor tiling and carpeting. The week after Wisdom will install the pool (8.5m x 3m fiberglass). Even if they can't finish by Christmas, it's not too much to expect them to finish soon after right? Hi Funk52, few of us are in similar situation. WH don’t want to commit to an estimated handover time. My SS only told me recently it might be end of January/ first week February. There is a 3 weeks close down which will slow every down in the new year I guess. Similar for me too no estimate PCI date r handover, we are also close to completion Re: Building with Wisdom Homes 15340Nov 25, 2019 9:11 am malypetu Hi There, Can anybody indicate how much should (adequate range) the Hydraulic Eng job cost? I understand the intricacies of the work hence the "range" in the question. Cheers $33k for mine Can someone please offer some advice? Im DESPERATE. Because I'm completely and utterly exhausted. How long are variations taking with other companies at the moment? We… 0 18460 In fairness nobody gave a crap about the ACCC and the gag clauses continued in the pro forma templates of a few other builders after the ACCC took on Wisdom, and more… 19 73443 Hi Everyone, I am exploring builder in NSW and received a very tempting quote from Wisdom home for their momentum series. I just want to know experience of building… 0 8233 |