Bits of action this week. Our tiler continued his work and Como have had some rectification works completed. A&L have been but they still need to come back. A carpenter came as well to close the manholes. I'm sure some other stuff went on as well.
I went out on Friday afternoon to check out progress from our fencer and our driveway pour (concrete was delayed so now we need to delay them till the weekend after we move, if they pour this week then there will be no way for our movers to get our stuff in as the back doors are now not accessible due to fences) and bumped in to our SS. He assured me 100% that handover will be this Friday 10th May. He has booked appliance install and is happy for us to go ahead with confirming movers and providing notice to our estate agent. 5 sleeps to go!!
YAY!!! so happy for you clareymoo how exciting! We are hoping our COO (Certificate of Occ.) gets approved this week so we could get the bank to inspect...looking forward to all those pics