Browse Forums Building A New House Re: Builder quotes 15 months from slab date 20May 07, 2019 5:15 pm steel alexp79 Theoretically, if one storey build: Yeah. I dont know any builders who will schedule works to happen at the same time that much. It can only be done with tradies who already worked together previously, use the right tools for the jobs (eg. robotic set out stations, etc.) and have their daily stations and materials optimally distributed in space, so they are not blocking each other. I believe up to 3x efficiencies can be easily achieved, but will require 100% onsite supervision and micromanagement. Although in most cases it is an art rather than science, but can be assisted through the computer simulation. Obviously, tradies are never paid on an hourly rate, they are paid agreed rate for the full job to be done, but eligible for bonuses or fines based on the quality and speed. Our external decking was only installed 2 months ago, and already moulded, with cracks, and some timber decolorated. The decking is in an exposed area, uncovered in our… 0 1464 Hi Mofflepop, I would recommend finding a building designer to prepare plans, they should design to your specified budget. The benefit is you can tender the project out… 9 22244 Although I am a big opponent of using waffle pod slabs over H2/P soils under any circumstances, in your case I would certainly opt in to keep piers under central… 1 2696 |