We did get a call from the electrician to have a chat which is something, although he wasn't aware that construction (frame) had even started. I've since received a text from Energex, so he's at least started lodging paperwork.
We've had more rain here and I just want the roof on! There is only about two days worth of carpentry work on the frame before the roof can go on, and it's so painful that this hasn't been able to be scheduled yet. Especially since the office manager pointed out in an email on 11 March that they needed to finalise my CABINETRY as a "matter of urgency" because the frame was unprotected. I have provided them with information either the same day or the next business day after it’s been requested, but it seems like we just keep getting pushed to the bottom of the pile. Hoping the whole build doesn’t continue like this