Browse Forums Building Standards; Getting It Right! Re: Edge beam on rolled fill? 8Jan 09, 2019 6:32 am Newbuild19 Hi just started building, however I’ve checked the engineering and states the slab is built on rolled fill (not controlled) 300mm and the edge beams are on this too. Can you confirm if that’s okay? waffle slab, as there was a cut and fill on my Slight sloped sight. Been approved by building surveyor but friend advised it can’t be on rolled fill? Thanks Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Yes this is in AS2870-2011 6.4.2 to be compacted with repeated rolling of an excavator or similar and in 150mm layers if not sand Hello everyone, After some suggestions and ideas about how to put a concrete path around the drop edge beam area on our new build. We are required to have a concrete path… 0 12875 The distance between my DEBs varies from 4.1m at the narrowest to 8.1m at the widest. 5 27328 |