Browse Forums Building A New House 1 Nov 02, 2018 8:29 am Hi first time posting on this forum. I am building Hamilton24 in Murrumba Downs. Started site work on 22 October after a long admin stage of around 4 months. Timeline 1. 05 June 2018 Land settlement done 2. 10 June 2018 prelim Quote from Plantation homes 3. 18June 2018 paid prelim deposit and signed revised quote 4. 28 June 2018 Soil test done. H1 type. Same as was in quote. 5. 11 July 2018 detailed sketch version 1 6. 25 July 2018 Colour Selection appointment 7. 27 July 2018 Acoustic Report receivd 8. 23 Aug 2018 Contract and Electrical appointment 9. 01 Sep 2018 Boundary Setback relaxation consent form received from neighbour. Requirement was 1.5 m from boundary. The planned build is 1.1 m from boundary. 10. 10 Sep 2018 construction loan application 10. 06 Sep 2018 Council Approval lodged 11. 24 Sep 2018 Council Approval received 12. 02 Oct 2018 Final drawings received 13. 10 Oct 2018 unconditional loan approval received. Aurhority to commence construction 14. 15 Oct 2018 pre site admin stage finished. File moved to construction 15. 22 Oct 2018 land scrape, cut and fill done 16. 30 Oct 2018 concrete footing 17. 31 Oct 2018 Slab poured Re: Hamilton24 Plantation Homes 3Nov 04, 2018 10:28 pm vasrsam Hi first time posting on this forum. I am building Hamilton24 in Murrumba Downs. Started site work on 22 October after a long admin stage of around 4 months. Timeline 1. 05 June 2018 Land settlement done 2. 10 June 2018 prelim Quote from Plantation homes 3. 18June 2018 paid prelim deposit and signed revised quote 4. 28 June 2018 Soil test done. H1 type. Same as was in quote. 5. 11 July 2018 detailed sketch version 1 6. 25 July 2018 Colour Selection appointment 7. 27 July 2018 Acoustic Report receivd 8. 23 Aug 2018 Contract and Electrical appointment 9. 01 Sep 2018 Boundary Setback relaxation consent form received from neighbour. Requirement was 1.5 m from boundary. The planned build is 1.1 m from boundary. 10. 10 Sep 2018 construction loan application 10. 06 Sep 2018 Council Approval lodged 11. 24 Sep 2018 Council Approval received 12. 02 Oct 2018 Final drawings received 13. 10 Oct 2018 unconditional loan approval received. Aurhority to commence construction 14. 15 Oct 2018 pre site admin stage finished. File moved to construction 15. 22 Oct 2018 land scrape, cut and fill done 16. 30 Oct 2018 concrete footing 17. 31 Oct 2018 Slab poured Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Ask for references and speak to them. If they are defensive or try to avoid the request, walk. 1 74701 I would never build with Fowler homes. I built with them in 2021 and till date maintenance issues are pending. All their existing trades and businesses don't work with… 14 105557 Hi there! Putting the feelers out there for those who have (or almost) built with Arli homes! Interested in your experiences who've built from their stock home designs… 0 23483 |