So far our timeline looks like this
Date council plans approved: 3rd May 2018
Date house demolished: 4th June 2018
Date garage door replaced: 20th July 2018 (got damaged during demolition)
Date land levelled: 1st August 2018
Date slab poured: 9th August 2018
Date Drainage commenced: 16th August 2018
Date Electrical services brought in: 31st August 2018
Date Frame delivered: 7th September 2018
Date Frame commenced: 10th September 2018
Date windows/doors delivered: 11th September 2018
Date windows/doors put into frame: 17th September 2018
Date first lot of bricks delivered: 24th September 2018
Date internal plumbing commenced: 24th September 2018
Date bricking commenced: 28th September 2018
Date internal plumbing completed: 2nd October 2018
Date scaffolding erected: 11th october 2018
So seems like we are a couple of months behind you guys!
We seem to be on a similar time line..... we are currently bricking 2nd story if only this stupid rain would go away..... fingers crossed for some sunshine to come