Hi all,
I'm starting a build thread so I can keep track of where I'm at.
Building in Two Wells, North of Adelaide.
28th April Land contracts signed
10th June Build contract signed
20th June bank appointment booked
29th June land settlement completed
Soil report ordered
6th July prelim working drawings received
23rd July Submitted working drawings with changes - bring on the big as* laundry!
6th August signed off final plans
13th July Received footings report
14th July started making selections appointments
28 August Plans submitted to council
29 November approved council plans finally received
20 December Bank loan settled - pending Approval to build letter
Christmas shutdown!
17th January - Construction Approval letter.. with no start date..
6th March slab poured
21 March Framing started
10 April Facsia and gutters installed
23 April Roof installed
30 April bricks started
4 June Bricks complete and cleaned
11 June Gyprock begun
29 June Locked up!
6 July Joinery completed
24th July painting started
6 August tiling completed
28 August PCI
10 September garage doors installed,external painting completed
13 September HANDOVER
5th October Floor tiling completed
10 October carpets laid
12 October MOVING DAY
16 October Driveways
23rd December 'landscaping'