I discussed this with my SS, he said he is working on a 40 Week timeline, (which I have no idea where he got that from) and he asked me to raise any concerns with CSR. I contacted CSR and she confirmed me that it is a 30 week contract, and to raise any issues back with SS. So there was definitely a ping-pong there and an opportunity for W to improve and better communicate.
My SS says we are tracking to milestones but my build time says 34 weeks and I've confirmed it's 34 weeks from excavation. I'm already at 34 weeks not including 3 week shutdown down period and I'm guessing I'm still 2 months from handover. Hope things pick up but I'd hope that wisdom also pay the per day cost for not meeting timeframes. Anyone know how much that is ?
We are going to find out this Friday, what's the process, what's involve and everything.