Add to around 7 issues remaining from pre-plaster to be fixed. They had put plaster without fixing and now had to cut the plaster.
The most amazing thing is pre-plaster given on 26/03/18. The plaster started on 05/4/18. The SS asked for recommendation from Engineers on 10/4/18 and they replied next day that the issues pointed in pre-plaster have to be fixed. So, those issues have not been completed even on 21/05/2018. This has caused major delay in progress of work.
How frustrating. I hope they fix it soon. Your facade is looking nice though.