Hello, been following this forum for a while but thought I'd post up my build so other people looking to build with Easystart Homes (Summit) can get an idea of what to expect.
* Late August - Deposit paid on land
* 31/08/17 - Signed PPA
* 12/10/17 - Drafting Complete
* 23/10/17 - Contract Signing
* 03/11/17 - Planning Approval
* 16/11/17 - Pre-Start Meeting
* 24/11/17 - Estimating Complete
* 05/12/17 - Drafting Complete
* 12/12/17 - Finance Approval
* 18/12/17 - Land Developer Approval
* 02/01/18 - Final Plans Signed
* 05/01/18 - Land Titles Issued
* 25/01/18 - Land Settlement
* 22/01/18 - Scheduling
* 12/02/18 - Siteworks Complete
* 14/02/18 - Slab Complete
* 16/03/18 - Brickwork Complete
* 13/04/18 - Roof Complete
* 30/04/18 - Ceilings Complete
* 07/05/18 - Plaster Set Complete
* 14/05/18 - Lock up
* 21/05/18 - Grano to Garage Complete
* 23/05/18 - Painter - Spray
* 25/05/18 - Ceramic Tiler