Browse Forums Building A New House Re: Aveling Build - Rosehill Waters 159May 11, 2018 8:59 pm Ok so according to Aveling last week wasn’t lock up 🤔 but we are at lock up now! 🙌🏻 Doors are on both externally and internally. Kitchen and bathroom cabinets due to go in next week, undercoat of the ceilings, doors and frames next week as well. External painting to start the end of the week and benchtops going in the following week. Bit of a blow that our bathroom and ensuite wall tiles won’t be in stock until June and if we wait it could mean a 2-3 week delay. We couldn’t find another tile we liked within the tile budget so we may have to wait. Going to have a look at the tile shop and pray they have some new selections! Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: Aveling Build - Rosehill Waters 160May 11, 2018 9:21 pm Sometimes the lack of communication can work in your favour, hopefully they held of sending the invoice for the extra week 😉 Feel sorry about your tile selection not being held for you. Thank you so much everyone. This all makes a lot of sense. I guess when you talk to a builder who butters up everything to look very polished, you get to start believing… 7 17630 Hi We have finally decided to complete a KDR on our corner plot in NE Melbourne suburbs. Given its a corner plot approx. 400 sqm just a standard design may not fit the… 0 8579 |