Take Two 117Apr 29, 2018 9:38 pm So, not a lot of progress in the last month. Emails to the builder remained unacknowledged and unanswered until I resend them with a "deadline" for reply, and the replies were a couple of minutes before the time specified. The one that started Ï am very dissatisfied.." has still not been addressed. I've been told twice now - two weeks apart - that the final tiles have arrived, but not which ones they were, or why they were late. I asked on 18 April if the house would be finished on time, with a request not to be ignored or any more game playing. That one got an almost immediate response - saying he wasn't ignoring me or playing games! Perhaps there are different definitions in the world in which he lives. And, of course, there is a new date for handover - 19 May. This will be 39 working weeks over the 30 week contract period. Don't quite know if I can remain civil in a face to face meeting. Visits to site earlier this month didn't show any further progress - still no base for water tanks, let alone the tanks themselves, no workmen on site, and couldn't really see much from the outside. Kitchen and laundry people let me know they would be on site on Friday, so I got to visit then. Door furniture was finally being installed - information on choices for this was originally given on 22 December, and confirmed in January - so no ignoring going on here! Anyway, tiling in bathrooms looks to be complete, balustrade in attic has finally been installed, and the laundry joinery was happening. It seems that the joiners also had a delay with the long kitchen benchtop - it's measurements were wrong, and the manufacturer then sent a new one - with exactly the same wrong measurements! Sorted out now, and it was being fitted as I watched. And now for the photos - whilst this may look like a lot of changes - it has taken a month to get to this point! Balustrade from the bedroomIs quite high - above waist height on me, so goo protectionLike ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Wardrobe in Main bedroomLike ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Ensuite shower with seat - waterproofedLike ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Ensuite shower with tiles and sunshineThere will be a slatted wooden seat on top. Looks like it will be a sunny way to start the day.Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Grouting completed for bathroom featureShows up the bamboo shapes much moreLike ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Long benchtopLike ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Laundry cabinets awaiting installationLike ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Laundry drawersLike ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Twenty days.... Variegated Take Two 119Apr 30, 2018 12:51 pm Thank you Trimum - I see that you are still not finished either! Last time i built, the builder went bankrupt. I've come to the conclusion that that is preferable, because at least you know the reason that nothing is happening, and that when the insurance things get themselves sorted out, you can get on with it again. This is just never-ending, and emotionally so debilitating, not to mention expensive - 9 months now paying both rent and mortgage. Variegated Re: Take Two 120Apr 30, 2018 3:09 pm Variegated Thank you Trimum - I see that you are still not finished either! Last time i built, the builder went bankrupt. I've come to the conclusion that that is preferable, because at least you know the reason that nothing is happening, and that when the insurance things get themselves sorted out, you can get on with it again. This is just never-ending, and emotionally so debilitating, not to mention expensive - 9 months now paying both rent and mortgage. Yes financially it’s horrific! We have been paying rent and mortgage for over a year, we have 8 more weeks of this, we have been very generous in giving our builder more than enough time to finish and have received as much of a guarantee as we can from them that we will have keys in 8 weeks time. Hi Mofflepop, I would recommend finding a building designer to prepare plans, they should design to your specified budget. The benefit is you can tender the project out… 9 21281 Hi, We're building a double-storey in Perth and I'm undecided with the kitchen sink situation. I'm set on having the main sink with dishwasher in the scullery - and… 0 21474 2 3406 |