Browse Forums Building A New House Re: Coral Homes - Hampton 26 - Tweed 20May 11, 2018 7:38 pm Hi Guys, Haven't posted since council approved our build but decided to jump on to share a few details on the progression so far as I found it helpful reading others "timelines" and I couldn't find any builds to follow that were the Hampton 26 by Coral. Start date- 29th March WEEK 1- Site scrap, plumbing, slab prep, builders fencing, port-a-loo, etc WEEK 2- Slab laid WEEK 3- Not a whole lot WEEK 4- Frame went up (bottom storey and top but no roof framing) WEEK 5- Roof framing to start the week, gutters and fascia followed WEEK 6- Roof tiles on top (not on garage roof yet), electrical rough in, aircon guys started something and bricks delivered I have been impressed with our site supervisor after what was a terrible experience with pre-site admin. Hopefully we continue in the right direction. This is us at the end of six weeks. Hoping for some brickwork to begin sometime towards the end of the week. Thanks mj-mac4 for the pic . Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Ask the council if there is a chance of getting build over easement exemption. Sometimes easements are unused and 24cm is not all that much. Good luck. And yes any builder… 2 13771 In Qld it is a requirement that a builder must have a cost breakdown, for building a home to the same specification, with the same inclusions and the same finish. So ask… 1 4346 Ask for references and speak to them. If they are defensive or try to avoid the request, walk. 1 74708 |