Based on the timeline M has given us, it will take up to 83 working days for everything to be done - making it virtually impossible for us to be in construction before the 90 day period finishes - meaning we will probably have to pay the $950 per month even whilst they aren't doing any work over those 30 days of shutdown?
Anyone else been in a similar situation before? Does M extend this period to take into account the industry shutdown?
Also they mentioned that if you signed the contract early they add additional days onto your 90 days. I.e. if you had until march 30 to sign ur contracts but signed on the 1st march they add an extra 29 days to your 90 days. At least that was what they told me...but as i said that was not in our tender so i told them in the nicest possible way i ain't paying regardless of how many days over