Hi all, I'm new to the forum.
I'm building a house with Mac jones. Whom I've always loved their designs.
Up until council stage I couldn't fault them. Now nothing seems to happen unless I contact them, then there's more forms to be filled out to do the next thing that could have been done 2 weeks prior. It's probably poor coordination on the project managers part. I understand there's more jobs than ours going. We've had our cut and fill done, were told there was a 2 week delay for the slab to be poured. Now it's been 30 days since anything has happened. The concrete was apparently booked in for yesterday. I've tried calling site supervisor to no avail.. anyone else experience similar problems? How did you deal with it?