Browse Forums Building A New House Re: Who is building with Beechwood 14913May 10, 2017 4:18 pm 20/11/15 - Settled land 06/11/15 - Request 1st tender BH 21/04/16 - Colour Selections and Contracts Signed 31/05/16 - Commencement Letter 24/06.16 - Started work onsite - cut and benching begun Re: Who is building with Beechwood 14914May 10, 2017 4:19 pm 20/11/15 - Settled land 06/11/15 - Request 1st tender BH 21/04/16 - Colour Selections and Contracts Signed 31/05/16 - Commencement Letter 24/06.16 - Started work onsite - cut and benching begun Re: Who is building with Beechwood 14918May 11, 2017 7:53 am newb Grace33 We have our PCI on Monday too. We still need carpets, appliances, and fly screens. With only 1 working day to go I am thinking it won't be finished either. how did you go Grace? Buildingabetterhome.blogspot.com.au Land deposit - Oct 14 Deposit - Jan 16 Land registered - June 16 Settlement - July 16 Colour selection and approval -Sept 16 Slab- Nov 16 Frame - Dec 16 Re: Who is building with Beechwood 14919May 11, 2017 7:57 am PCI went well, thanks for asking newb!!! Our site supervisor (Garry) has been great. Our quick build time has come down to him booking in trades and being on top of everything. So we had our appointment at 10am on Monday. We walked through with Garry. He had put blue stickers on marks on the wall but nothing major. The front door tile entry was the biggest problem because it wasn't level. He said he will get the tiler back out to correct it. We found a hairline crack in a tile in the ensuite right up the top. Our watertank pipes need to be re-done and put in the ground, so our screen can be put in the right spot. We were happy to sign off and start the process to get the keys. He said the appliances wont go in until a day before handover because they've had alot of theft atm especially in Wadalba. So now they wait, to save paying for the appliances again. After the PCI I emailed beechwood and they sent out the final invoice the next day, we got $1100 back on site fencing because our neighbours had there fence up already. I sent it to my bank and now I am just waiting on a valuator to view the property. I also applied for a occupation certificate on Friday but haven't heard anything yet. Meanwhile Garry will fix up some of the issues and it will get another clean. Hoping to get the keys by the end of next week. Then the fun begins. Buildingabetterhome.blogspot.com.au Land deposit - Oct 14 Deposit - Jan 16 Land registered - June 16 Settlement - July 16 Colour selection and approval -Sept 16 Slab- Nov 16 Frame - Dec 16 Re: Who is building with Beechwood 14920May 11, 2017 8:06 am bkalm Hi Everyone, So i have started reading this post from the beginning and am about halfway through. It's only taken about a week. Lol. Loving seeing how everybodies builds were going and have picked up some great tips. We are currently waiting for our land to be registered in Green Orchids, Nowra. Building the Verdelho guest with a few mods. I am sure there will be many Questions later on but i do have one now. When we first approached BW we were told our site costs would be $45. When we received our tender site costs are now $60 and we have additional site costs of $15??? I should also say we are getting our land through Beechwood but seperately to the house. Our rep told us about this land from the get go, saying it had been looked at previously but sale fell through and that's when the $45 site costs came up. it is a slightly sloping piece of land but can't believe how much the site costs have gone up. Can anyone shed some light as to costs? Unfortunately i haven't caught up to the newer posts yet. Is anyone else building in Green Orchids? Thanks and can't wait to catch up on the rest of this thread. Welcome bkalm. You where lucky they originally told us our site cost would be 50k then our first tender came back with 110k sight costs. There where a few different reasons that just added up. Elvis has left the building... The site supervisor quit after 2 month on the project. I guess he was just instructed to bark at people, but didn't like when he was… 26 22252 Following these simple steps will help you mitigate unwanted costs, have your expectations met and give… 0 4974 you need to understand the breakdown of warranties. 90 warranty is considered as minor defects rectification period where as the longer ones are more major/structural… 1 5880 |