Browse Forums Building A New House Re: Anyone bought in Emerald Hills Leppington NSW? 173May 04, 2017 7:56 am Hi all, Those that are building with Fairmont Homes NSW in Stage 1B - how are your approvals process going for DA/CC? I've just signed off on submission plans and council lodgement documents. How are your experiences so far? Thanks Lot 1140 😊 Building with Fairmont Homes NSW in Emerald Hills Estate, Leppington. Re: Anyone bought in Emerald Hills Leppington NSW? 174May 04, 2017 9:08 am Hi all, We are building with Wisdom Homes in Stage 1B- currently awaiting CDC approvals. Like many of you, we are hoping to be in by Christmas, although I think that's a stretch at this point. Looking forward to moving into the suburb! ![]() Re: Anyone bought in Emerald Hills Leppington NSW? 175May 04, 2017 10:07 am ![]() Hi all, Those that are building with Fairmont Homes NSW in Stage 1B - how are your approvals process going for DA/CC? I've just signed off on submission plans and council lodgement documents. How are your experiences so far? Thanks Lot 1140 😊 No news, which is quite frustrating. Any ideas if Fairmont will be going thru DA or CDC? From what i hear CDC is a quicker process. Re: Anyone bought in Emerald Hills Leppington NSW? 176May 04, 2017 10:31 am ![]() ![]() Hi all, Those that are building with Fairmont Homes NSW in Stage 1B - how are your approvals process going for DA/CC? I've just signed off on submission plans and council lodgement documents. How are your experiences so far? Thanks Lot 1140 😊 No news, which is quite frustrating. Any ideas if Fairmont will be going thru DA or CDC? From what i hear CDC is a quicker process. Hi LT, Fairmont Homes NSW will be lodging with council for DA/CC not via CDC.. well for my lot I can confirm this. CDC is "usually" a quicker process, if the development complies with the requirements. However Camden Council isnt too bad in regards to turnaround times for DA/CC. Perhaps you can email them for an update on your specific lot. Good luck! I still believe I won't be the new home till Early 2017 but we shall see. 😊 Building with Fairmont Homes NSW in Emerald Hills Estate, Leppington. Re: Anyone bought in Emerald Hills Leppington NSW? 177May 04, 2017 6:21 pm ![]() Hi all, Those that are building with Fairmont Homes NSW in Stage 1B - how are your approvals process going for DA/CC? I've just signed off on submission plans and council lodgement documents. How are your experiences so far? Thanks Lot 1140 😊 Our builder is going through the CDC route - our plans were submitted a week ago and we asked for a copy of the plans they submitted - and they submitted the 2015 plans vanilla plans. ![]() After a few emails the new building plans are being withdrawn and submitted - builder claims it shouldn't lengthen the approval time by much ![]() Re: Anyone bought in Emerald Hills Leppington NSW? 178May 11, 2017 12:12 pm Hello All, just joined today. bought a lot in stage 2 and was informed that the registration is now delayed from Dec 2017 to Feb 2018. Has anyone else got any new updates? I am worried as i have already signed contract with house builder and have to pay a for each month of delay
![]() Thanks again Simeon for being so elaborate. Appreciate it. Its gives us a very idea. Kind Regards 4 4335 If so what were the "special circumstances" under which it was granted? "Note: If the development consent is for 'dual occupancy' an owner-builder permit can only be… 0 14952 Landscape Design Parramatta We have been doing a large amount of landscape design work in Sydney… 0 3 |