Browse Forums Building A New House Re: SJD Homes. Who's built with them. 249Nov 02, 2016 7:10 pm Update KDR: ---------------- Planning/Quotes Jan to Jul 2016 --------------------------------- [SPOILER] 12/01/2016 first quotation 16/01/2016 second quotation 12/03/2016 third quotation and floor plan draft 24/04/2016 first draft full drawings Comment:***** five star service from SJD sales (Leigh) 29/05/2016 colour selection 15/06/2016 fourth quotation 04/07/2016 section29a consent to demolish approved Comment: was expecting this to delay us but was wrong. (Took 2 days) 06/07/2016 pre-approved loan 09/07/2016 Signed building contract/drawings 20/07/2016 Electricity meter removed Comment: United Energy were very responsive in getting this done (5days) 21/07/2016 demolition quotes [/SPOILER] Demolition/Permits/Plans-Approvals-Aug 2016 ---------------------------------------- [SPOILER] 03/08/2016 engaged independent inspector DARBECCA to oversee stages 05/08/2016 asset protection approved 15/08/2016 gas meter removed Comment:very slow process. (Took 25 days) 16/08/2016 asbestos removal 18/08/2016 cancelled insurance 18/08/2016 started demolishing house Comment:EXPRESS DEMOLITION-*****Great service took 5 days fully cleared. 22/08/2016 finance approved 22/08/2016 requested underground electricity pit from UE 23/08/2016 land cleared-Waiting for sewer capping 23/08/2016 paid deposit to builder 23/08/2016 confirmed all stages to be overseen by DARBECCA 24/08/2016 received loan contract 26/08/2016 signed loan contract Comment:whole loan process was a disaster...(took 2.5 months) 26/08/2016 received underground electricity pit quote 3phase($3600). Replied to proceed. 29/08/2016 building permit approved(waiting for copies of stamped plans). Proposed start build date mid Sept 30/08/2016 sewer capped 31/08/2016 received Plans stamped and approved [/SPOILER] Pre-Build Sept 2016 --------------------- [SPOILER] 01/09/2016 Electricity pit amount deducted 02/09/2016 Construction loan ready by bank 07/09/2016 site supervisor assigned, works to begin Monday yay! 07/09/2016 requested demolisher temp to be remove to allow allow for builder temp fencing 08/09/2016 demolisher's temp fence removed 09/09/2016 site cut and builder fence up 13/09/2016 bricks delivered (rainy-no activity) 14/09/2016 (rainy-no activity) 15/09/2016 (rainy-no activity) 16/09/2016 (rainy-no activity) 19/09/2016 piers bored and filled 20/09/2016 electricity meter installed 22/09/2016 under slab plumbing 22/09/2016 electricity pit installed Comment:very slow process took 25 days 26/09/2016 no activity 27/09/2016 no activity 28/09/2016 no activity (steel delivered) 29/09/2016 PRE-pour base steel preparation done 29/09/2016 DARBECCA inspection performed at 3pm (paid invoice) Comment: 4-Defects reported. However the overall inspection reported as very well presented base. Happy with that . Waiting for SS to confirm fixes. Confirmed minor defects will be done on the pour day [/SPOILER] Build Oct 2016 --------------------- [SPOILER] 03/10/2016 slab poured, yay! 04/10/2016 invoiced, sent bank progress payment claim for base 05/10/2016 some soil was cleared and rubbish-bobcat looks to have been operated on the slab, can see the tracks of dirt(been rainy so may wash off) 06/10/2016 no activity 07/10/2016 no activity 10/10/2016 bank confirmed BASE progress payment processed 11/10/2016 frames started 12/10/2016 frames continued 13/10/2016 more frames continued yay! Can now see the Porch area and what will be the balcony 14/10/2016 first floor chipboard installed 17/10/2016 first floor frames started 18/10/2016 trusses delivered 19/10/2016 more work on first floor frames looks completed 20/10/2016 electricity meter installed 21/10/2016 invoiced for frame, requested bank progress payment 24/10/2016 window frames delivered 25/10/2016 ground level windows installed 26/10/2016 no activity 26/10/2016 DARBECCA inspection done 27/10/2016 informed SS of defects by report. SS will look at fixing major ones 27/10/2016 tin roof gutters delivered 28/10/2016 gutters started 29/10/2016 gutters finished 31/10/2016 tin roof started [/SPOILER] Build Nov 2016 01/11/2016 public holiday 02/11/2016 insulation started Re: SJD Homes. Who's built with them. 257Nov 13, 2016 8:15 pm Update KDR: ---------------- Planning/Quotes Jan to Jul 2016 --------------------------------- [SPOILER] 12/01/2016 first quotation 16/01/2016 second quotation 12/03/2016 third quotation and floor plan draft 24/04/2016 first draft full drawings Comment:***** five star service from SJD sales (Leigh) 29/05/2016 colour selection 15/06/2016 fourth quotation 04/07/2016 section29a consent to demolish approved Comment: was expecting this to delay us but was wrong. (Took 2 days) 06/07/2016 pre-approved loan 09/07/2016 Signed building contract/drawings 20/07/2016 Electricity meter removed Comment: United Energy were very responsive in getting this done (5days) 21/07/2016 demolition quotes [/SPOILER] Demolition/Permits/Plans-Approvals-Aug 2016 ---------------------------------------- [SPOILER] 03/08/2016 engaged independent inspector DARBECCA to oversee stages 05/08/2016 asset protection approved 15/08/2016 gas meter removed Comment:very slow process. (Took 25 days) 16/08/2016 asbestos removal 18/08/2016 cancelled insurance 18/08/2016 started demolishing house Comment:EXPRESS DEMOLITION-*****Great service took 5 days fully cleared. 22/08/2016 finance approved 22/08/2016 requested underground electricity pit from UE 23/08/2016 land cleared-Waiting for sewer capping 23/08/2016 paid deposit to builder 23/08/2016 confirmed all stages to be overseen by DARBECCA 24/08/2016 received loan contract 26/08/2016 signed loan contract Comment:whole loan process was a disaster...(took 2.5 months) 26/08/2016 received underground electricity pit quote 3phase($3600). Replied to proceed. 29/08/2016 building permit approved(waiting for copies of stamped plans). Proposed start build date mid Sept 30/08/2016 sewer capped 31/08/2016 received Plans stamped and approved [/SPOILER] Pre-Build Sept 2016 --------------------- [SPOILER] 01/09/2016 Electricity pit amount deducted 02/09/2016 Construction loan ready by bank 07/09/2016 site supervisor assigned, works to begin Monday yay! 07/09/2016 requested demolisher temp to be remove to allow allow for builder temp fencing 08/09/2016 demolisher's temp fence removed 09/09/2016 site cut and builder fence up 13/09/2016 bricks delivered (rainy-no activity) 14/09/2016 (rainy-no activity) 15/09/2016 (rainy-no activity) 16/09/2016 (rainy-no activity) 19/09/2016 piers bored and filled 20/09/2016 electricity meter installed 22/09/2016 under slab plumbing 22/09/2016 electricity pit installed Comment:very slow process took 25 days 26/09/2016 no activity 27/09/2016 no activity 28/09/2016 no activity (steel delivered) 29/09/2016 PRE-pour base steel preparation done 29/09/2016 DARBECCA inspection performed at 3pm (paid invoice) Comment: 4-Defects reported. However the overall inspection reported as very well presented base. Happy with that . Waiting for SS to confirm fixes. Confirmed minor defects will be done on the pour day [/SPOILER] Build Oct 2016 --------------------- [SPOILER] 03/10/2016 slab poured, yay! 04/10/2016 invoiced, sent bank progress payment claim for base 05/10/2016 some soil was cleared and rubbish-bobcat looks to have been operated on the slab, can see the tracks of dirt(been rainy so may wash off) 06/10/2016 no activity 07/10/2016 no activity 10/10/2016 bank confirmed BASE progress payment processed 11/10/2016 frames started 12/10/2016 frames continued 13/10/2016 more frames continued yay! Can now see the Porch area and what will be the balcony 14/10/2016 first floor chipboard installed 17/10/2016 first floor frames started 18/10/2016 trusses delivered 19/10/2016 more work on first floor frames looks completed 20/10/2016 electricity meter installed 21/10/2016 invoiced for frame, requested bank progress payment 24/10/2016 window frames delivered 25/10/2016 ground level windows installed 26/10/2016 no activity 26/10/2016 DARBECCA inspection done Comment: Again, a well presented frame reported. Shows quality of their work 27/10/2016 informed SS of defects by report. SS will look at fixing important ones 27/10/2016 tin roof gutters delivered 28/10/2016 gutters started 29/10/2016 gutters finished 31/10/2016 tin roof started and finished [/SPOILER] Build Nov 2016 01/11/2016 public holiday 02/11/2016 insulation started 05/11/2016 bricks delivered 08/11/2016 SS walk through frame with fixes. 09/11/2016 brick layer started job 10/11/2016 bricks we're laid, garage wall /some pluming done Re: SJD Homes. Who's built with them. 260Nov 26, 2016 11:55 am Hey Jclw, how're you going with the build? The slab will be poured on our block on Monday Are you getting the concreter to do the paving around the property after the build is completed? Are you getting the driveway from SJD? If not then who you going with? If you could please share the concreter's details as we are getting the driveway and alfresco area done later on. Cheers I haven’t. But have a Lowe Design home. Not only did I find Matt Lowe patronising and a bully, but the home is NOT TO CODE. I have water coming through the bricks… 1 15423 Hi everyone. I am a single mother with little daughter, living in a small tourist town in WA Australia. I am thinking to install security screens to all the doors and… 0 32655 First time poster long story short we are planning knocking down rebuilding a house in Wavell Heights We are thinking to go with Omni built homes as they are but flexible… 0 17676 |