Browse Forums Building A New House Re: SJD Homes. Who's built with them. 153Sep 14, 2016 9:13 am Update KDR: ---------------- Planning/Quotes Jan to Jul 2016 --------------------------------- [SPOILER] 12/01/2016 first quotation 16/01/2016 second quotation 12/03/2016 third quotation and floor plan draft 24/04/2016 first draft full drawings Comment:***** five star service from SJD 29/05/2016 colour selection 15/06/2016 fourth quotation 04/07/2016 section29a consent to demolish approved Comment: was expecting this to delay us but was wrong. Took 2 days 06/07/2016 pre-approved loan 09/07/2016 Signed building contract/drawings 20/07/2016 Electricity meter removed Comment: United Energy were very responsive in getting this done.5days 21/07/2016 demolition quotes [/SPOILER] Demolition/Permits/Plans-Approvals-Aug 2016 ---------------------------------------- [SPOILER] 03/08/2016 engaged independent inspector DARBECCA to oversee stages 05/08/2016 asset protection approved 15/08/2016 gas meter removed Comment:very slow process. Took 25 days 16/08/2016 asbestos removal 18/08/2016 cancelled insurance 18/08/2016 started demolishing house Comment:EXPRESS DEMOLITION-*****Great service took 5 days fully cleared 22/08/2016 finance approved 22/08/2016 requested underground electricity pit from UE 23/08/2016 land cleared-Waiting for sewer capping 23/08/2016 paid deposit to builder 23/08/2016 confirmed all stages to be overseen by DARBECCA 24/08/2016 received loan contract 26/08/2016 signed loan contract Comment:whole loan process was a disaster...took 2.5 months 26/08/2016 received underground electricity pit quote 3phase($3600). Replied to proceed. 29/08/2016 building permit approved(waiting for copies of stamped plans). Proposed start build date mid Sept 30/08/2016 sewer capped 31/08/2016 received Plans stamped and approved [/SPOILER] Pre-Build Sept 2016 --------------------- 01/09/2016 Electricity pit amount deducted 02/09/2016 Construction loan ready by bank 07/09/2016 site supervisor assigned, works to begin Monday yay! 07/09/2016 requested demolisher temp to be remove to allow allow for builder temp fencing 08/09/2016 demolisher's temp fence removed 09/09/2016 site cut and builder fence up 13/09/2016 bricks delivered Re: SJD Homes. Who's built with them. 157Sep 20, 2016 4:56 pm Update KDR: ---------------- Planning/Quotes Jan to Jul 2016 --------------------------------- [SPOILER] 12/01/2016 first quotation 16/01/2016 second quotation 12/03/2016 third quotation and floor plan draft 24/04/2016 first draft full drawings Comment:***** five star service from SJD 29/05/2016 colour selection 15/06/2016 fourth quotation 04/07/2016 section29a consent to demolish approved Comment: was expecting this to delay us but was wrong. Took 2 days 06/07/2016 pre-approved loan 09/07/2016 Signed building contract/drawings 20/07/2016 Electricity meter removed Comment: United Energy were very responsive in getting this done.5days 21/07/2016 demolition quotes [/SPOILER] Demolition/Permits/Plans-Approvals-Aug 2016 ---------------------------------------- [SPOILER] 03/08/2016 engaged independent inspector DARBECCA to oversee stages 05/08/2016 asset protection approved 15/08/2016 gas meter removed Comment:very slow process. Took 25 days 16/08/2016 asbestos removal 18/08/2016 cancelled insurance 18/08/2016 started demolishing house Comment:EXPRESS DEMOLITION-*****Great service took 5 days fully cleared 22/08/2016 finance approved 22/08/2016 requested underground electricity pit from UE 23/08/2016 land cleared-Waiting for sewer capping 23/08/2016 paid deposit to builder 23/08/2016 confirmed all stages to be overseen by DARBECCA 24/08/2016 received loan contract 26/08/2016 signed loan contract Comment:whole loan process was a disaster...took 2.5 months 26/08/2016 received underground electricity pit quote 3phase($3600). Replied to proceed. 29/08/2016 building permit approved(waiting for copies of stamped plans). Proposed start build date mid Sept 30/08/2016 sewer capped 31/08/2016 received Plans stamped and approved [/SPOILER] Pre-Build Sept 2016 --------------------- 01/09/2016 Electricity pit amount deducted 02/09/2016 Construction loan ready by bank 07/09/2016 site supervisor assigned, works to begin Monday yay! 07/09/2016 requested demolisher temp to be remove to allow allow for builder temp fencing 08/09/2016 demolisher's temp fence removed 09/09/2016 site cut and builder fence up 13/09/2016 bricks delivered (rainy-no activity) 14/09/2016 (rainy-no activity) 15/09/2016 (rainy-no activity) 16/09/2016 (rainy-no activity) 19/09/2016 piers bored and filled I haven’t. But have a Lowe Design home. Not only did I find Matt Lowe patronising and a bully, but the home is NOT TO CODE. I have water coming through the bricks… 1 14365 Hi everyone. I am a single mother with little daughter, living in a small tourist town in WA Australia. I am thinking to install security screens to all the doors and… 0 24742 First time poster long story short we are planning knocking down rebuilding a house in Wavell Heights We are thinking to go with Omni built homes as they are but flexible… 0 16278 |