We have our colours appointment next week, and I'm just wondering what timeframe we could reasonably expect for our build to commence? In reviewing the contract, it states (from memory) that following receipt of all essential information (obviously this would include Boutique applying for and receiving the Building Permit) the commencement of the build will begin within 28 days.
If we sign next week, are plans submitted to obtain a permit fairly quickly? Would love to hear other's experiences.
TIA
new estate or knock down rebuild?
from building permit approval to site start, 1 week for me.
Hi kdring
New estate for us. Land is titled.
What was the length of time between your colours appt and your permit being approved?