Did coral tell you that they will calculate the days they need to pay you once you reach PCI? Our 175 day build ended on Thursday so I emailed our cso and she said all that happens at the end. Thanks
Yeah I emailed the accounts lady today... I hope it's an actual payment not a credit or something... how much do you have left?
The painters started 6 weeks ago but after 1 day said they wouldn't go any further because the plaster work was so bad. The plasterer come back and said it wasn't his fault so for the last 4 weeks we have had engineers, representatives from the frame and gyprock company doing tests as the roof has cracked a fair bit in certain parts of the house mainly the kitchen. They put it down to the house settling so the plaster is supposed to start re-plastering the roof today then painters to start on Monday.
I'd say we still have a months worth of work plus all the things we have picked up already that we aren't happy with! Our SS left just as the gyprock issue come up so its been a sh*t few weeks. Hats off to you for handling your situation so well.
How long do you think you've got left?