Week 39 - Painting still continuing, builder has stated it will be finished early this week, not convinced at the current speed as there is still work outside and we can see some walls/woodwork inside that still needs to be painted.
The only other thing completed this week was the range hood & ducting was installed...
Wednesday of this week was also the contacted completion date, so we are now into the added days for rain, I only estimated 15 days from the information on the BOM website, but I am sure they will class days that had 0.1mm of rain at 2am as a rain day that meant they could not work. I am sure they will do anything to get out of paying a penalty.
Still can't get any date for Practical completion, the customer service person seems to be very good at dodging that question. I am just getting so frustrated as today the 4 double beds we order for the kids are ready and snooze want to deliver, they would hold onto them for another couple of weeks, but not until the end of June. So the cars will now have to be parked outside so we can store the beds in the garage, and when we will move it will probably take us 2 journeys with the removalist, so will add another $400 to the cost. Thank you Allcastle.