24-03-2016 Moved Out
29-03-2016 Gas Abolished by Jemena.
04-04-2016 Demo Begins (Democorp), Rawson SS assigned, but I don't know who it is. Edit: (Had I bothered to read the attached letter I would have seen who my SS is)
11-04-2016 Demo Complete. Awesome job by Democorp, they are a class act and I would highly recommend them.
13-04-2016 SS picked up file from Head Office.
14-04-2016 Clearance Certificate Received and forwarded to Rawson
19-04-2016 Peg Out Done
20-04-2016 Rawson Fencing is up
21-04-2016 Met with SS on site to go over any questions we might have about the process.
02-05-2016 Scraping in progress.
05-05-2016 Screw Piers installed.
09-05-2016 Under slab plumbing.
12-05-2016 Waffle Pods and reo.
16-05-2016 Slab
23-05-2016 Frames Delivered
29-05-2016 Windows Delivered
30-05-2016 Framing Started
07-06-2016 Framing and Windows Level 2
08-06-2016 Framing Completed
25-06-2016 Bricks Arrived
11-08-2016 Brickwork Complete (7 Weeks from arrival)
20-08-2016 Gutters, Fascia and roof completed
14-10-2016 All cladding done. Scaffolding removed. Electrical and plumbing rough in complete.
04-11-2016 Plasterboard and Waterproofing done
21-04-2017 Handover