Browse Forums Building A New House Re: Beaumont Hills Custom Build - Brick Stage 41Aug 08, 2015 11:28 pm 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Beaumont Hills Custom Build - Brick Stage 44Aug 09, 2015 1:03 am 11/11/13- dep paid 4/4/14- settlement Feb '15- DA app 6/8/15- CC site works begin 19/8/15- Formwork 25/8/15- slab 3/9/15- elect. appt 13/10/15 - frame started 19/10- bricks started 31/10 - roof done Re: Beaumont Hills Custom Build - Brick Stage 46Aug 09, 2015 5:31 pm 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Beaumont Hills Custom Build - Brick Stage 47Aug 09, 2015 5:50 pm 11/11/13- dep paid 4/4/14- settlement Feb '15- DA app 6/8/15- CC site works begin 19/8/15- Formwork 25/8/15- slab 3/9/15- elect. appt 13/10/15 - frame started 19/10- bricks started 31/10 - roof done Re: Beaumont Hills Custom Build - Roof done! 50Aug 10, 2015 10:42 pm 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Beaumont Hills Custom Build - Roof done! 52Aug 14, 2015 2:04 pm 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Beaumont Hills Custom Build - Roof done! 53Aug 22, 2015 12:11 am 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Beaumont Hills Custom Build - Roof done! 55Sep 01, 2015 12:18 am 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Beaumont Hills Custom Build - Roof done! 57Sep 05, 2015 10:01 am I really wanted this, but did not think about it until it was too late. I wish I had it. 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Beaumont Hills Custom Build - Roof done! 58Sep 22, 2015 12:24 pm Just a few more progress photos if anyone is still following my thread lol Gyprock/plastering expected to finish today. Next two weeks would be internal fittings and doors. My house is taking shape now. I went there on a saturday and really good to see people working on my site. Bought some beers and hopefully it inspired them to work faster lol Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: Beaumont Hills Custom Build - Roof done! 59Sep 22, 2015 6:15 pm Good to see it taking shape. Looks great. 11/11/13- dep paid 4/4/14- settlement Feb '15- DA app 6/8/15- CC site works begin 19/8/15- Formwork 25/8/15- slab 3/9/15- elect. appt 13/10/15 - frame started 19/10- bricks started 31/10 - roof done If this is a custom build then I would expect the builder to set out the door frame closer to the wall to avoid the gap between architrave and the wall and or specify… 9 6274 Thanks again Simeon for being so elaborate. Appreciate it. Its gives us a very idea. Kind Regards 4 1998 Even if it's not being sub-divided and you want to keep it as Torrens title, you will still need to talk to a town planner or Council themselves, to see if they will allow… 1 6834 |