Browse Forums Building A New House Re: Beaumont Hills Custom Build - Brick Stage 41Aug 08, 2015 11:28 pm 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Beaumont Hills Custom Build - Brick Stage 44Aug 09, 2015 1:03 am 11/11/13- dep paid 4/4/14- settlement Feb '15- DA app 6/8/15- CC site works begin 19/8/15- Formwork 25/8/15- slab 3/9/15- elect. appt 13/10/15 - frame started 19/10- bricks started 31/10 - roof done Re: Beaumont Hills Custom Build - Brick Stage 46Aug 09, 2015 5:31 pm 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Beaumont Hills Custom Build - Brick Stage 47Aug 09, 2015 5:50 pm 11/11/13- dep paid 4/4/14- settlement Feb '15- DA app 6/8/15- CC site works begin 19/8/15- Formwork 25/8/15- slab 3/9/15- elect. appt 13/10/15 - frame started 19/10- bricks started 31/10 - roof done Re: Beaumont Hills Custom Build - Roof done! 50Aug 10, 2015 10:42 pm 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Beaumont Hills Custom Build - Roof done! 51Aug 14, 2015 12:34 pm firsthome2 You could look at epoxy for garage as well, not sure how much it will cost you. I had included in my tender. Thanks, I'll do a research on that post-completion. My "Post-completion" list is piling up. I have a few regrets now, where I could have included upgrades in the tender. Re: Beaumont Hills Custom Build - Roof done! 52Aug 14, 2015 2:04 pm only if we ever build again. Can't imagine going through the stress again. I missed a lot of things as well, some were interpretation of the sales talk and what is in the contract. 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Beaumont Hills Custom Build - Roof done! 53Aug 22, 2015 12:11 am Any progress on your build? 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Beaumont Hills Custom Build - Roof done! 54Aug 31, 2015 7:56 pm Sorry hasnt updated for a while. Went for a short holiday and other things on my plate aside from the stress of building. Anyway, facade is taking shape now with the renders. Builder had a bit of hard time with the modern structuring so it took them a bit of time. Anyway, see photos below: Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Once the scaffoldings are gone then I hope We get a great view of the house Targetting to do electricals this week. Re: Beaumont Hills Custom Build - Roof done! 55Sep 01, 2015 12:18 am looks nice, but hard to see how the full house will look like. is this a full corner window? was it upstairs? 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Beaumont Hills Custom Build - Roof done! 56Sep 03, 2015 3:10 pm Yes this one is upstairs. Full corner window. Apparently they had to have it custom made so took time to have it delivered in the site Re: Beaumont Hills Custom Build - Roof done! 57Sep 05, 2015 10:01 am I really wanted this, but did not think about it until it was too late. I wish I had it. 18/03/15 Deposit 02/09/15 CDC 22/09/15 Slab 05/12/15 Frames 15/12/15 Brick started. 11/04/16 Roof start 04/05/16 Roof finish 09/07/16 Gyprock. Re: Beaumont Hills Custom Build - Roof done! 58Sep 22, 2015 12:24 pm Just a few more progress photos if anyone is still following my thread lol Gyprock/plastering expected to finish today. Next two weeks would be internal fittings and doors. My house is taking shape now. I went there on a saturday and really good to see people working on my site. Bought some beers and hopefully it inspired them to work faster lol Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Re: Beaumont Hills Custom Build - Roof done! 59Sep 22, 2015 6:15 pm Good to see it taking shape. Looks great. 11/11/13- dep paid 4/4/14- settlement Feb '15- DA app 6/8/15- CC site works begin 19/8/15- Formwork 25/8/15- slab 3/9/15- elect. appt 13/10/15 - frame started 19/10- bricks started 31/10 - roof done If this is a custom build then I would expect the builder to set out the door frame closer to the wall to avoid the gap between architrave and the wall and or specify… 9 6278 Thanks again Simeon for being so elaborate. Appreciate it. Its gives us a very idea. Kind Regards 4 1998 Even if it's not being sub-divided and you want to keep it as Torrens title, you will still need to talk to a town planner or Council themselves, to see if they will allow… 1 6842 |