Browse Forums Building A New House Re: Alkira Homes Elyse 15 Sydney Northern Beaches 11Oct 19, 2014 10:47 pm looking good! .. just read your latest blog posting. It's exciting to be able to see the shell completed as that is the most visual part of noticing any sort of progress. I guess once the build moves to internal there's no way to know unless you walk inside daily ... Re: Alkira Homes Elyse 15 Sydney Northern Beaches 12Oct 20, 2014 11:35 am sydneyalkirabuild Hi all. An update covering the last few weeks. Not too much on there... a few pics of the completed front though. http://sydneyalkira.blogspot.com/2014/1 ... er-14.html Ur house looks beautiful. Great colours Re: Alkira Homes Elyse 15 Sydney Northern Beaches 13Oct 22, 2014 5:24 pm Hi Deluded & DG85. Thanks for the comments! yes, we're really pleased with the way the colours came together. We were a bit uncertain during the selection phase, but thankfully it worked out! Whilst the contract prohibits you heading on site without supervision, we can see fairly well from just outside the property to see if there's any meaningful change inside. We also intend to arrange regular visits through the site supervisor so hopefully we'll still be able to provide regular updates on the blog & on here, and also get some pics. Re: Alkira Homes Elyse 15 Sydney Northern Beaches 14Oct 31, 2014 5:32 pm Hi, We are going tobuild a same home too.I have one concern about that void area ,is it bit narrow ?their display home looks all good as it's much wider. Re: Alkira Homes Elyse 15 Sydney Northern Beaches 15Nov 01, 2014 1:47 pm Hi all, we're now 29 weeks in to the build and the gyprocking and cornicing has largely been completed. We've had a few issues with our fireplace, but continue to make steady progress. Here's a link to our latest blog for more details... http://sydneyalkira.blogspot.com/2014/1 ... cking.html Hi Blackbeauty. We're really pleased with the width of the void area. Any wider and we think it'd be a poor use of space. It's around 2.3m wide. At the top there's a small angled section where the roof cuts across (not sure if that's only there due to our modifications or if it's standard on all builds). We're having glass installed in the stairwell and the area between the void and the upstairs hallway so that'll help open it up and let the light flow throughout also. Hope that helps. Re: Alkira Homes Elyse 15 Sydney Northern Beaches 16Nov 01, 2014 4:57 pm Hi, checked your blog today looks like everything is moving along smoothly and at a steady pace. Not so for us, our bricklayers started 7 weeks ago today and have only just starting on the first floor. At this rate I'm wondering if we'll have roof tiles on before the Christmas break. Re: Alkira Homes Elyse 15 Sydney Northern Beaches 17Nov 04, 2014 3:01 pm Hi Kach. Are you building with Alkira also? Out of curiosity, if you are building with them, how long did they advise you that each stage of the build would take? We have emails from the sales team where they clearly stated it would take 4-5 weeks per stage and that the contract would state a 36 week build time. We're currently running at a little over 6 weeks per stage, and the contract ended up with a 45 week build time. We provided the head of Alkira homes with copies of the emails the sales staff sent us when we disputed the build time, and he simply said (in so many words) tough luck. He wouldn't budge. His position was of course helped by the fact that we'd paid $15k+ in tender and contract costs at that point in time. Re: Alkira Homes Elyse 15 Sydney Northern Beaches 18Nov 05, 2014 5:37 am blackbeauty Hi, We are going tobuild a same home too.I have one concern about that void area ,is it bit narrow ?their display home looks all good as it's much wider. Their display home is also 2.3 m wider and that looks good..we are going with the 38sq elyse and the area is a bit narrow and we had to widen it to 2.3 to get the same size of the display home thereby reducing the size of study and guest bed Alkira homes - Elyse15 Re: Alkira Homes Elyse 15 Sydney Northern Beaches 19Nov 07, 2014 12:21 pm Thanks a lot to Raina & Sydneyalkirabuild . we did not increase the width to 2.3m, it's only 1.8m! we are going to get some kind of special ceiling light to solve the problem. Our building contract just started, SS said the slab could be done before Xmas. Re: Alkira Homes Elyse 15 Sydney Northern Beaches 20Nov 07, 2014 6:59 pm sydneyalkirabuild Hi Kach. Are you building with Alkira also? Out of curiosity, if you are building with them, how long did they advise you that each stage of the build would take? We have emails from the sales team where they clearly stated it would take 4-5 weeks per stage and that the contract would state a 36 week build time. We're currently running at a little over 6 weeks per stage, and the contract ended up with a 45 week build time. We provided the head of Alkira homes with copies of the emails the sales staff sent us when we disputed the build time, and he simply said (in so many words) tough luck. He wouldn't budge. His position was of course helped by the fact that we'd paid $15k+ in tender and contract costs at that point in time. Yes we are building with Alkira, however no one ever advised us of the length of time each stage would take to complete. We have read plenty of blogs to know that 4 to 6 weeks would be considered reasonable. We are just disappointed that no information is forth coming, we ended up asking the bricklayers for a time frame and they gave us a week. That would have ment that they finished today but I drove past this afternoon and they're still not done. We had a DA approved last year and here is the condition that was imposed by Northern Beaches council: 1 5023 Hi there! Putting the feelers out there for those who have (or almost) built with Arli homes! Interested in your experiences who've built from their stock home designs… 0 61042 No idea about the driveway question, but your price for a house that size including landscaping seems very good! 1 22188 |