First of all - I would like to get an idea on peoples building time frames. So far this is our time frame of things:
11/08/14 - Pre-start meeting
13/08/14 - Final costings received and signed off on
03/09/14 - Final Documents received and signed
22/09/14 - Site works commenced
26/09/14 - Slab went down
03/10/14 - Soakwells installed
08/10/14 - Bricks delivered
17/10/14 - Brickwork commenced
07/11/14 - Brickwork complete
11/11/14 - Roof framing commenced
12/11/14 - Fascia complete
13/11/14 - Roof framing completed
13/11/14 - Gutters complete
17/11/14 - Colorbond commenced
19/11/14 - Colorbond completed
19/11/14 - Plumbing commenced
20/11/14 - Plumbing completed
26/11/14 - Electrical wiring completed
02/12/14 - Drywall commenced
04/12/14 - Drywall completed
08/12/14 - Ceiling & cornices delivered
09/12/14 - Ceiling commenced
15/12/14 - Cornices completed
15/12/14 - Ceiling completed
19/12/14 - Wooden doors installed
19/12/14 - LOCK UP!!!
Xmas Break
09/01/15 - Delivery of tiles, plumbing stuff, door handles and bath
12/01/15 - Cabinets delivered
14/01/15 - Cabinets completed
14/01/15 - Robe, pantry & linen shelving installed
15/01/15 - Tile screeding & waterproofing
19/01/15 - Tiling commenced
27/01/15 - Tiling completed (except 2 missing tiles and kitchen)
27/01/15 - Grano to garage
29/01/15 - Toilets delivered
03/02/15 - Kitchen benchtop installed
04/02/15 - Painting commenced
06/02/15 - Kitchen splashback tiles and final bath tiles completed
10/02/15 - Plumbing completed
11/02/15 - Electrical completed
13/02/15 - Painting completed
17/02/15 - Shower screens installed
18/02/15 - Rangehood installed
18/02/15 - Bobcat levelled areas for paving
20/02/15 - Bathroom mirrors and sliding robe doors installed
23/02/15 - Door handles and towel rails installed
27/02/15 - Carpet installed
28/02/15 - Paving completed to driveway and alfresco
05/03/15 - Vinyl flooring installed
05/03/15 - Flyscreen doors installed
10/03/15 - Blinds installed
11/03/15 - Window flyscreens installed
11/03/15 - Final Site Clean
12/03/15 - Oven installed
12/03/15 - Silicon to bench edges
13/03/15 - PCI!!
14/03/15 - Blinds completed (kitchen & laundry)
14/03/15 - Insulation commenced!
19/03/15 - Garage Door installed
23/03/15 - HANDOVER!!!
It all seems to be going quicker than I expected so it would be good to see what sort of timeframe I should expect for the rest of the build!