Browse Forums Building A New House Re: Fairmont Home builders - South Australia 2Sep 02, 2014 12:22 pm Thread: viewtopic.php?f=31&t=66299 Slab: 16/6/14 Frame: 4/7/14 Roof: 22/7/14 Lock Up: 20/8/14 Fixing: 26/8/14 PCI: 9/10/14 Handover: 20/10/14 Re: Fairmont Home builders - South Australia 19Sep 26, 2014 8:24 pm Our PCI in original letter was mid Feb but there was a note to add approx. 6 weeks for xmas and because we were having flooring, this took us to end of march. Our build was single story but it was complicated. Hopefully it will be all smooth sailing for you and you will be in before xmas. I am pretty sure they prioritised builds to get it done before xmas which is one of the reasons ours stagnated Re: Fairmont Home builders - South Australia 20Sep 26, 2014 8:39 pm I hope you're right ! Even though it meant yours plateaued for a while at that stage. I hear very good things about the houses once their completed, its just the whole build stage with them that is frustrating. So it's good to hear from you that it was a happy ending! Fairmont Homes Contract signed: July 2013 Slab: May 2014 Frame: July 2014 Roof: 1/8/14 1st fix electrical: 24/9/14 Gyprock: 29/9/14 Brickwork completed: 6/10/14 Handover: 14/12/14 Adam Baines Grad Cert Bldg Surv / Grad Dip Bldg Surv / MSAAPA Accredited Building Professional APB20210035 Builders Lic 183023 Pest Control Lic 84868 Ph 0412202336 PO… 3 46843 Well these guys are not looking good... I sent them a written enquiry last week and they have not yet replied. If they cannot respond to a simple… 4 10636 If you don't want to annoy the neighbours then simply get yourself some good head phones. For me the sound is much better using headphones. The NCC (National Construction… 1 26171 |