Browse Forums Building A New House Re: Custom Design on 5 Acres Northern NSW - Earth Works Star 65Jun 01, 2014 4:32 pm Build thread http://tinyurl.com/llgc7yk Re: Custom Design on 5 Acres Northern NSW - Earth Works Star 66Jun 01, 2014 5:18 pm Blog http://tobuildahomeimprobable.blogspot.com.au/ Settlement Apr Council Jul Contracts Dec Earthworks Dec Frames Jan Trusses Feb Roof Feb Windows Mar Re: Custom Design on 5 Acres Northern NSW - Earth Works Star 67Jun 09, 2014 7:03 pm Blog http://tobuildahomeimprobable.blogspot.com.au/ Settlement Apr Council Jul Contracts Dec Earthworks Dec Frames Jan Trusses Feb Roof Feb Windows Mar Re: Custom Design on 5 Acres Northern NSW - Earth Works Star 69Jun 10, 2014 7:33 am Build thread http://tinyurl.com/llgc7yk Re: Custom Design on 5 Acres Northern NSW - Earth Works Star 73Jun 10, 2014 7:26 pm Blog http://tobuildahomeimprobable.blogspot.com.au/ Settlement Apr Council Jul Contracts Dec Earthworks Dec Frames Jan Trusses Feb Roof Feb Windows Mar Re: Custom Design on 5 Acres Northern NSW - Earth Works Star 77Jun 16, 2014 8:08 pm Look at that! Lovely I would have loved to watch ours get poured, but since it was a surprise slab, it didn't happen! Haha Bring on the frame stage!! Thread: viewtopic.php?f=31&t=66299 Slab: 16/6/14 Frame: 4/7/14 Roof: 22/7/14 Lock Up: 20/8/14 Fixing: 26/8/14 PCI: 9/10/14 Handover: 20/10/14 Re: Custom Design on 5 Acres Northern NSW -Slabbed (Week3)!! 78Jun 17, 2014 11:53 am Thanks guys. I think the boxing was taken off yesterday, and now it will sit for a few days, or week or so. Bl**dy Telstra. How hard is it to get a simple answer of getting cable from the street to the house. We aren't in a NBN area, so will have regular ADSL. I ring them, and they say the builder has to arrange it. THe builder calls, and they say it up to the client. GRRRR. I am so close to tell them where to put their phone connection. If I could find out if it will be about the same cost now, or later, I would wait til later, when we would be sure if we wanted it connected. Oh well, life isn't meant to be simple. Re: Custom Design on 5 Acres Northern NSW - Slabbed (Week 3) 79Jun 17, 2014 5:20 pm It looks fantastic and HUGE! Can't wait to see your frames going up! Ah don't get me started on Telstra lol Build thread http://tinyurl.com/llgc7yk Re: Custom Design on 5 Acres Northern NSW - Slabbed (Week 3) 80Jul 06, 2014 11:08 am Well it's been a few weeks since I posted. The slab was left for a week, and nothing happened at all on site. The beginning of week 5 saw the trench being dug to bring services (elect & water and should be phone grr). Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Approx 120m of trench. They will leave most of this trench open and hopefully we can get an answer from Telstra. Towards the end of the week (now nearly 2 weeks) we saw the delivery of the frames! Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ These were wall frames, and then the roof frames were delivered early this week. Other than that not much had happened on site, until DH went out on Wednesday! Landscape Design Parramatta We have been doing a large amount of landscape design work in Sydney… 0 3 ideal house depends on the site and location as much as internal floor plan....what is the distance from the house to all four boundaries, where is north, describe your… 3 15142 Hi, I am wondering if anyone has built with Montgomery in the last few years on the Northern Beaches? I don't see the see them around, as I would love to ask how happy… 0 3186 |