"Upon completion of the work the subject of a Provisional Sum or on installation of an item being a Prime Cost Item or at the next progress payment notice, the Builder shall provide the Owner with an itemised statement setting forth the final costs for the work or the items, calculated in accordance with the provisions of Clauses 9(a) and (b) hereof and the Contract Price shall be amended accordingly"
So if you have this clause or similar, they are contractually obliged to provide the breakdown of the costs for provisional sums. Tell the lady at RI to do her job
Tis a bit late for me now as we paid Final Invoice in Dec. Hopefully, this will help Abby
Doesn't mean that you couldn't get a cheque if your provisional sum amounts were less than allowed for in the contract. You can guarantee if they were more they would have charged you for it