Hey guys I have been stalking this forum for so long and am excited to start my very own thread! Took 34 weeks exactly from earthworks until keys!
[b:2ffpg4gw][i:2ffpg4gw]Time Line[/i:2ffpg4gw][/b:2ffpg4gw]
15th October 2013 - Approached HGWA
9th November 2013 - Offer on block
5th February 2014 - Final Contract with HGWA signed
6th March 2014 - Colour Appointment (selections on page 3, 10 & 13)
20th March 2014 - Block Settlement
11th April 2014 - Pre Start
22nd May 2014 - Final Documents signed
23rd June 2014 - Earthworks
9th July 2014 - SLAB!!!
30th July 2014 - Brickies Started
2nd September 2014 - Brickies Finished
3rd September 2014 - Roof Chippies started
26th September 2014 - Colorbond Started
3rd October 2014 - Windows
7th October 2014 - Drywall started
27th October 2014 - Ceilings started
10th November 2014 - Doors delivered for lock up!!!
11th November 2014 - Lockup!
14th November 2014 - Painters
26th November 2014 - Cabinets Delivered!!!!!!!
27th November 2014 - Cabinets installed (pics on page 91)
1st December 2014 - Powder Room Basin and bench top installed
2nd December 2014 - Bath installed in 2nd bathroom & Plumbing done
3rd December 2014 - Tile Meeting
4th December 2014 - Waterproofing
4th December 2014 - Garage Grano
9th December 2014 - Tiling started (Photos page 96 & 97)
10th December 2014 - Bathroom, Laundry, Scullery & Ensuite Benchtops (Photos page 96)
12th December 2014 - Pavers delivered
19th December 2014 - Kitchen BENCHTOPS (photos page 99)
7th January 2015 - Plumbing (toilets, tapware, freestanding bath etc all installed - Photos on page 101)
7th January 2015 - Electrical (downlights, light switches etc all installed)
8th January 2015 - Splashback tile done
8th January 2015 - Cornices done in Portico & finished in ensuite
8th January 2015 - Hot water system installed
14th January 2015 - Floor Tiling (pics page 104)
19th January 2015 - Painters started
19th January 2015 - Range hood installed
20th January 2015 - Paving started (Alfresco finished - driveway nearly done)
23rd January 2015 - Oven Installed
23rd January 2015 - Insulation
27th January 2015 - Shower screens, vinyl sliders and mirrors hung
28th January 2015 - Pavers finished
28th January 2015 - Air Con installed
29th January 2015 - Outside Painting started
29th January 2015 - House Clean
30th January 2015 - Front door stained - outdoor painting finished
2nd February 2015 - Flyscreens
3rd February 2015 - Garage Doors
3rd February 2015 - Site Clean
4th February 2015 - Carpets
ALL FINISHED
12th February 2015 - PCI
16th February 2015 - KEYSS!!!!!
Some Decorated rooms
Painted Recesses - Page 124
Sheers (living room) - Page 126
Ensuite painted black wall - Page 128
Black paint in kitchen - Page 131
Front landscaping - Page 132
Finished activity room - Page 133
Finished Scullery - Page 134
Master bedroom Feature wall - Page 135
Master WIR - Page 139