Browse Forums Building A New House Re: Building a new home with Burbank 3Jan 06, 2014 8:32 pm Burbank Custom DS 23/01 Slab 14/02 Frame 15/04 Lockup 13/06 Fixing 02/09 PCI 11/09 Settlement My Build:viewtopic.php?f=31&t=68855 Blog:http://ourmentone3850.blogspot.com.au Re: Building Custom Double Storey with Burbank 8Jan 11, 2014 8:28 pm Burbank Custom DS 23/01 Slab 14/02 Frame 15/04 Lockup 13/06 Fixing 02/09 PCI 11/09 Settlement My Build:viewtopic.php?f=31&t=68855 Blog:http://ourmentone3850.blogspot.com.au Re: Building Custom Double Storey with Burbank 10Jan 11, 2014 11:46 pm Burbank Custom DS 23/01 Slab 14/02 Frame 15/04 Lockup 13/06 Fixing 02/09 PCI 11/09 Settlement My Build:viewtopic.php?f=31&t=68855 Blog:http://ourmentone3850.blogspot.com.au Re: Building Custom Double Storey with Burbank 12Jan 12, 2014 8:51 pm Burbank Custom DS 23/01 Slab 14/02 Frame 15/04 Lockup 13/06 Fixing 02/09 PCI 11/09 Settlement My Build:viewtopic.php?f=31&t=68855 Blog:http://ourmentone3850.blogspot.com.au Re: Building Custom Double Storey with Burbank 16Jan 13, 2014 4:31 pm Burbank Custom DS 23/01 Slab 14/02 Frame 15/04 Lockup 13/06 Fixing 02/09 PCI 11/09 Settlement My Build:viewtopic.php?f=31&t=68855 Blog:http://ourmentone3850.blogspot.com.au Re: Building Custom Double Storey with Burbank 17Jan 13, 2014 4:57 pm Burbank Custom DS 23/01 Slab 14/02 Frame 15/04 Lockup 13/06 Fixing 02/09 PCI 11/09 Settlement My Build:viewtopic.php?f=31&t=68855 Blog:http://ourmentone3850.blogspot.com.au Re: Building Custom Double Storey with Burbank 19Jan 18, 2014 6:17 pm Congratst to you! They started building mine too, I couldn't believe they did the earthwork on a 43 degree HOT day last week! Finally find some ppl building with burbank here, will read you stories and learn. Building Custom D Storey with Burbank - Stormwater Pipes are 20Jan 20, 2014 5:17 pm Week 3 - Stormwater & Sewer Pipes are IN !!!!
Mon 20th Jan - Sun 26th Jan 2014 Mon 20th Jan - Day 8 Underground Pipes!!! Yes they are truely now underway and made a mess of my wonder and FLAT block I am looking forward to alot of progress this week as its going to be much much cooler than last week [mid 20's to low 30's].. Well, anything better than 44 degrees days I say.. The underground Pipes are in Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Official Burbank Sign IN Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ And also the delivery of the red sand, ready for the slab??? Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ Fingers cross for a concrete slab by end of the week Tue 21st Jan - Day 9 Today it seems they have finished working on the underground pipes, sight has been cleared and levelled I am assuming the fluorescent green Pipe are water Pipes and fluorescent Pink is for the sewer?? Anyone know? Like ⋅ Add a comment ⋅ Pin to Ideaboard ⋅ TO BE Continued..... refer page 2 This certainly doesn't look good. I would be engaging with an independent inspector to have a look at this. As for the unscheduled site visits, most builders are quite… 1 28285 Hi All, Recently we have signed a contract with Burbank and we are not aware that they have just DORSET, SURREY, HAMPSHIRE, KENT, PILBARA and REDGUM bricks from PGH are… 0 3127 It seems very clear to me that your contract states that a security account does NOT need to be established so the answer to the builder is NO. If in doubt find a contract… 1 8473 |